How Long Does a Kitchen Remodel Take? Houston Timeline (2026)

By , Co-Founder & Principal Designer · 30+ years remodeling Houston homes

TL;DR

Most Houston kitchen remodels take 6–12 weeks once demo starts. Full gut remodels with layout changes and custom cabinetry typically run 10–14 weeks. Cabinet lead time (6–10 weeks) sets the schedule more than anything else.

Most Houston kitchen remodels take 6–12 weeks once demo starts, as of 2026. A straightforward remodel that keeps the existing layout takes about 6–8 weeks. Full gut remodels with layout changes and custom cabinetry typically run 10–14 weeks. The biggest factor isn't the crew. It's cabinet lead time: custom cabinets take 6–10 weeks from order to delivery, so we order them first and do demo and rough-in while they're being built.

Here is what a typical kitchen remodel looks like week by week, what sets the schedule, and what makes one run long.

How long does a kitchen remodel take?

Typical Houston timelines as of October 2026, counted from the day demo starts:

Scope Typical timeline What drives it
Straightforward remodel, same layout 6–8 weeks New cabinets, countertops, backsplash, lighting and fixtures in the existing footprint.
Most Houston kitchen remodels 6–12 weeks Custom cabinet lead time and how much of the layout changes.
Full gut remodel with layout changes 10–14 weeks Wall removal, relocated plumbing and custom cabinetry.
Historic home (1920s–1940s) 14–20 weeks Longer custom cabinet lead times and structural, plumbing or electrical updates found during demo.

For what each scope costs, see our Houston kitchen remodel cost guide.

What happens each week of a kitchen remodel?

A typical 10-week Houston kitchen remodel, once demo starts:

  1. Weeks 1–2: Demo, rough plumbing and electrical, framing for any layout changes.
  2. Weeks 3–4: Drywall, paint prep and flooring prep. Cabinets arrive.
  3. Weeks 5–6: Cabinet install. Countertops are templated. Backsplash prep.
  4. Weeks 7–8: Countertop install, backsplash tile, lighting, plumbing fixtures, appliances in.
  5. Weeks 9–10: Punch list, final trim, touch-up and final cleaning.

Every kitchen is different, and what stretches a schedule is usually a little of everything: scope, cabinet lead time, framing and relocated plumbing, and what turns up behind the walls.

Why do cabinets set the kitchen remodel schedule?

Custom cabinets typically take 6–10 weeks from order to delivery, which is longer than most of the construction itself. A typical cabinet schedule:

  • Week 1: We submit shop drawings for your approval.
  • Weeks 2–7: Cabinets are in production.
  • Weeks 7–8: Cabinets are delivered to the job site.

That's why we order cabinets first. Demo, plumbing, electrical and drywall happen during the build period, so the cabinets arrive when the room is ready for them, and your kitchen isn't torn out while you wait. Once they're delivered, installation takes about 1–2 days. Learn more about custom cabinet costs and lead times.

What makes a kitchen remodel take longer?

  • Layout changes. Removing a wall or moving the sink to an island adds framing, plumbing and electrical work, and that adds time as well as cost. Keeping a workable layout is the easiest way to save both.
  • Surprises behind the walls. Structural, plumbing or electrical problems uncovered during demo are one of the most common reasons a schedule moves.
  • Older homes. A full kitchen remodel in a historic 1920s–1940s River Oaks home typically takes 14–20 weeks, because those homes often need updates behind the original walls and matching custom cabinetry takes longer to build.
  • Custom cabinetry. Custom cabinets take longer than stock or semi-custom. The extra time buys cabinets built to your exact space instead of stock sizes.

What happens before demo starts?

The timelines above start at demo. Before that, every project goes through the same three steps:

  1. Free in-home consultation. We walk the space with you, learn how you use the kitchen, and talk through budget and priorities.
  2. Design and quote. Layout, cabinet specifications, finish selections and a line-item quote.
  3. Cabinet order. Shop drawings are approved and the cabinets go into production, which starts the 6–10 week clock.

Selections are the biggest part of the schedule you control. Choosing cabinets, countertops, tile and appliances early lets us order materials before they're needed, so nothing waits on a late decision. See how we run kitchen remodeling projects.

Can you live at home during a kitchen remodel?

Yes. Most of our Houston clients stay in the home throughout the remodel. We set up a temporary kitchen, contain the work area with dust barriers and coordinate the schedule to keep disruption down.

Does a kitchen remodel take longer than a bathroom remodel?

Project Typical timeline once demo starts
Guest bath 3–4 weeks
Primary bath with custom tile and glass 5–7 weeks
Luxury spa primary bath 7–10 weeks
Kitchen remodel 6–12 weeks

Kitchens take longer mainly because of cabinetry, countertops and appliances. Planning both at once? See our Houston bathroom remodel cost guide, or check kitchen remodeling in Katy if you're on the west side.


McKelvey Designs is a family-owned remodeling company serving Katy and the Greater Houston area since 1991. NARI member. Get a free in-home consultation or call (281) 499-0581.

Ready to start your remodel?

Free in-home consultation. We'll listen to your vision, walk the space, and give you a real plan with real numbers.

Frequently Asked Questions

How long does a kitchen remodel take?

As of 2026, most Houston kitchen remodels take 6–12 weeks once demo starts. A straightforward remodel that keeps the existing layout takes about 6–8 weeks. Full gut remodels with layout changes and custom cabinetry typically run 10–14 weeks.

What takes the longest in a kitchen remodel?

Cabinets. Custom cabinetry takes 6–10 weeks from order to delivery, which is almost always the longest item on the schedule. We order cabinets first so demo, plumbing, electrical and prep work happen while they're being built.

How long does it take to install kitchen cabinets?

Once custom cabinets are delivered, installation itself takes about 1–2 days. Countertops are templated after the cabinets are in, then installed along with the backsplash, lighting, plumbing fixtures and appliances.

Can I live in my house during a kitchen remodel?

Yes. Most of our Houston clients stay in the home throughout the remodel. We set up a temporary kitchen, contain the work area with dust barriers and coordinate the schedule to keep disruption down.

Why do some kitchen remodels take longer than quoted?

The most common reasons are usually cabinet lead times and structural, plumbing or electrical problems uncovered during demo. Older homes are the biggest risk: a full kitchen remodel in a historic 1920s–1940s River Oaks home typically takes 14–20 weeks.

Does a kitchen remodel take longer than a bathroom remodel?

Usually. A Houston guest bath takes 3–4 weeks and a primary bath with custom tile and glass takes 5–7 weeks, compared with 6–12 weeks for most kitchens. The difference is mostly cabinetry, countertops and appliances.